
WEST APPROACH
Traducción al Español de esta página.
Seismic safety retrofit work on the West Approach — bordered by 5th Street and the Anchorage at Beale Street — involved completely removing and replacing this one-mile stretch of Interstate 80 and six on- and off-ramps in its original footprint. This work occurred while more than 280,000 vehicles flowed daily in the midst of this essential construction.
The West Approach originally had one foundation system supporting both an upper and lower deck configuration from 3rd Street to Beale Street. Each deck now has its own independent column and foundation support system, a crucial aspect of making the West Approach seismically sound. The roadways between 3rd and 5th Streets are parallel concrete decks that transition into the double-deck configuration as drivers approach the West Span of the Bay Bridge.
Work on the 72-year-old structure began in 2003, and completed in early 2009. To keep traffic flowing, and to enable work to occur in a densely populated residential and commercial hub south of Market Street, builders performed a “retrofit by replacement,” one of the most complex projects in Caltrans history.
To minimize disruptions to the neighborhood, and to keep the bridge’s traffic moving, the project was performed in a series of six elaborate stages, including a series of lane shifts, regular lane and ramp closures, and one partial bridge closure.
Each of the six stages of retrofit work followed a carefully staged formula to meet seismic safety standards. A temporary structure was built and vehicles were rerouted to it. The old structure was then demolished, and work began on the new structure in the original footprint. Drivers were then rerouted back onto the completed replacement structure, and the temporary structure was demolished.
For more than a year eastbound motorists were diverted onto a temporary structure tucked beneath westbound traffic coming off the Bay Bridge. Those eastbound motorists now have unobstructed views for most of the way to the Bay Bridge. The opening of the permanent structure carrying eastbound traffic was the final major traffic shift — from a temporary structure to a permanent one — for the West Approach.
KEY FACTS
Over 1.5 million lbs. of structural steel
Over 3.2 million lbs. of reinforcing steel installed
Over 106,000 cubic yards of concrete poured
Approximately 750,000 lbs. of miscellaneous metal
Over 60,000 cubic yards of excavation
Over 10 million lbs. of pile casings
25,000 linear feet of piles







